Revised Planning, Design, and Construction timeline for 2007 Bond Program Projects
Henry Gideon presented the Board with a revised planning, design, and construction timeline for the 2007 bond program projects. He explained that circumstances have changed and the beginning phase of the timeline would be flexible.
Betty Richardson presented phase two of the design process. Mrs. Richardson stated that the new high school would be a learning resource for our students and the district would look at equitable services and resources for all students. Mrs. Richardson reviewed types of spaces that our students need and stated that they may look at creating smaller spaces (pods) to put students together. She explained that this would allow for more collaboration and would help build relationships. Mrs. Richardson reviewed possible program offerings and added that she would like to include a distance learning center at the new high school. Mrs. Richardson stated that both high schools would have specialized programs at their campuses.
Mrs. Bullock asked when the Board would make a decision on naming the new high school. She cautioned against referring to the high school as Cedar Creek High School until a name has been decided upon. President Allen agreed and stated that naming the high school would be discussed further at the team building workshop next month. Mrs. Halladay would like to allow the community to give input on naming the new school. Mr. Gideon stated that there have been some community members that have expressed an interest in being involved in the planning process. Superintendent Emanuel stated that the naming of the high school would be included on the September team building agenda.